Slab & Wall Modelling (Revit)

Continues to the blogger of CBWD, I would like to share more detail about the slab and wall opening modelling and the usage of this model and detail workflow. This model can large help for construction cost, mep coordination and building progress.

Workflow of creating slab and wall opening model
1. Create door opening, Louvre opening and Acess opening
Create architectural opening base on preliminary architectural model automatically .
2. Create MEP Opening
Create MEP opening base preliminary MEP model automatically. Magical is one of the rebut addin to create MEP opening base routing and wall
3. Update opening base on CBWD needs
Update the opening manually base on the comments on CBWD. This stage may need large manually works.
4. Lock the frozen opening
After the CBWD is approved and available for construction, lock the related opening. This stage is to confirm the opening model match site construction .

Usage of Slab and wall opening model
1. Benefits for future MEP rearrangements
While the opening model is match with site and will not suddenly removed or relocated, the MEP engineers can use the opening model for their future coordination. MEP rearrangement is very common in a design and build project. With the opening model, MEP engineer can more easy to find the way to reroute the pipe system or duct system by using existing opening.
2. QS patyroll for opening refill contractor
In the past, the price of opening refill works is hard to estimate because QS do not know the exact number of opening. For Building engineer, they need to spend lots of time to count the number by reviewing tons of drawings.With the opening, we can generate a schedule of opening and the size, purposes of the openings.

Tips and recommendations
1. After the approval of the CBWD drawings, there are two concepts will affect the opening models.. They are DAms and RBW. DAms means the opening in approval drawing is relocated and resubmitted the drawing for approval. However, hand draft and sketch always occurs so they may not reflect into the opening model. For this kind of DAMs, we can’t well manage. Therefore, a backup of opening model for approval CBWD drawing is important and update the Dams opening in to live model if possible. RBW means request builder words. It not only relate to opening but also all the additional builder works such as defect, drilling works, etc. In this part, RBW is another addition cost which hard to estimate. If possible, record all the RBW dams opening can also help for QS payroll and manage the unreasonable RBW.

2. Separate opening under different CBWD Submissions
Create several Worksets to store openings and frozen the workset while the CBWD is approved. It Also, it benefit for multiple workers while different people may responsible for different workplace of CBWD.

Expression
In my project, I have not good use for wall and slab opening. The reason is the MEP model is nit under my control. It is control by another company and do not put efforts on the opening model. So the poor situation make the opening not match with site which is unsuitable and unreliable for the usages above. Therefore, I strongly hope this blogger can attend me to improve in my future project.

留言

此網誌的熱門文章

Combined Builders Work Drawings Production (Revit)
合併建造工程圖(CBWD)製作(Revit)

Producing Combine Builders Work Drawings (CBWD) for opening construction is an intricate process that involves a harmonious collaboration of Architecture, Structure, and Building Services. CBWD encompasses various types of openings, such as wall openings (doors, windows, AC ducts, fire suppression pipes, etc.), slab openings (tower cranes, material hoists, AC risers, etc.), and beam openings (primarily for drain pipes). Throughout the CBWD workflow, each stakeholder plays a crucial role in ensuring that construction adheres to standards and client requirements. For example, architects specify door and window sizes, engineers assess the impact of openings on the main structure and provide calculations, and building services engineers reroute Mechanical, electrical, and plumbing ( MEP) systems to accommodate opening locations. 製作合併建造工程圖(CBWD)以進行開口建設是一個複雜的過程,需要建築、結構和建築服務的協同合作。CBWD包括各種類型的開口,如牆壁開口(門、窗戶、空調管道、消防供水管道等)、板條開口(塔吊、物料提升機、空調升降機等)和梁開口(主要用於排水管道)。在整個CBWD工作流程中,每個利益相關者都在確保建設符合標準和客戶要求方面發揮...

Facade Cast-In Embed Modelling (Revit) & AIP Drawing Production
幕墻預埋件模型及相關圖紙製作

Drawing plays a crucial role in design, approval, and construction processes. In the past, hand sketches and tools like AutoCAD were used for creating drawings. In this context, I'll share a modern method involving models and Revit, using the example of cast-in embed AIP drawings. 繪圖在設計、審批和施工過程中扮演關鍵角色。過去,人們使用手繪草圖或AutoCAD等工具來製作圖紙。在這個背景下,我將分享一種現代方法,涉及模型和Revit,以幕墻預埋件模型和製作AIP圖紙為例。 Creating a Cast-In Embed Model: 創建 幕墻預埋件模型 : The first step involves gathering essential information, such as detailed drawings, engineering requirements, standards, and sketches. Next, automation is key. Using a mullion model, cast-in embeds can be automatically generated with Dynamo, based on mullion locations. After the draft model is ready, it's shared with engineers through BIM Viewer for review and coordination. 第一步涉及收集關鍵資訊,如詳細圖紙、工程要求、標準和草圖。接下來,自動化是關鍵。使用窗柱模型,可以透過Dynamo自動生成與窗柱位置相關的鑄造埋入物。草稿模型準備好後,通過BIM Viewer與工程師共享,以便進行審查和協調。 Starting AIP Drawing Production: 開始AIP圖紙製作: Following drawing standards an...